Line 8 of the Chengdu Metro (Chinese: 成都地铁8号线; pinyin: Chéngdū Dìtiě Bā Hào Xiàn) is a line on the metro network in Chengdu, Sichuan, China. The first phase opened on 18 December 2020.[1]
The line runs from northeast to southwest and avoids the city center of Chengdu. It also connects the Wangjiang and Jiang'an campuses of Sichuan University.
Remove ads
History
- On 11 July 2016, NDRC approved the 3rd phase expansion for the Chengdu Metro, consisting of Line 6 phase 2 and 3, Line 8 Phase 1, Line 9, Line 10 Phase 2, Line 17 Phase 1, and Line 18.[2] The third phase was to be simultaneously built with the already under construction second phase.
- On 11 April 2020, Chengdu Metro reported that track-laying for Line 8 was completed.[3]
- On 8 August 2020, Line 8 's whole line power network passed quality assessment.[4]
- On 18 Dec 2020, Line 8 Phase 1 opened along with: Line 6 Phase 1/2/3, Line 9 Phase 1, Line 17 Phase 1, Line 18 Phase 2, marking the completion of all Phase 2 and 3 projects.[5]
- On 18 May 2020, Line 8 Phase 2, Line 27 Phase 1, Line 30 Phase 1 started construction. This marks the date all 4th Phase projects started construction.[6]
- On 27 March 2023, Line 8 Phase 2 finished Longgang~Lianhua section tunnel work. Line 8 Phase 2 entered railroad construction, electrics, and refurbishment stage.[7]
- On 19 December 2024, Line 8 Phase 2 opened for service.[8]