Dhansiri–Zubza line

Railroad in India From Wikipedia, the free encyclopedia

Remove ads

The Dhansiri–Zubza Line is a single-track railroad under construction between the two major cities of the Indian state of NagalandDimapur and Kohima. The line starts from Dhansiri junction near Dimapur Railway Station to Kohima Zubza Railway Station. It is a part of Northeast Frontier Railway zone of Indian Railways.

Quick Facts Overview, Status ...
Remove ads

Main line

Summarize
Perspective

History

First announced in 2006, the line is currently expected to open in December 2029.[1] As part of the Indian Railway's ambitious plan to connect all the capitals of the north-eastern states by broad gauge rail link, railway minister Suresh Prabhu laid the foundation stone of the 88-km rail line to bring Kohima, the capital of Nagaland, on the railway map of India. The project will be executed in three phases.

  • The first phase involves the construction of Dhansiri to Shokhuvi (16  km) line.
  • The second phase involves Shokhüvi to Khaibung. (30  km)
  • The third phase involves Khaibung to Zubza. (45  km)

Route

Stations are in the following order on the Dhansiri–Zubza line (Dimapur-Imphal line): Dimapur, Dhansiripar, Shokhüvi, Molvom, Khaibung, Pherima, Pephema, Mengujuma and Kohima.

The alphabetical list of stations with codes is as follows:

More information Station Code, Station Name ...

Current status

  • 2024 Jun: 52% work on the 82.5 km line from Dimapur to Zubza near Kohima has been completed, railway has requested the Nagaland Government to expedite the land acquisition process which is holding up progress on this rail link.[2][3] Molovom-Pherima (14 km) completion target date is October 2026, Pherima-Zuzba target completion date is December 2029 (May 2025 official update).[4]
Remove ads

Railway in Nagaland

Zubza-Kohima line

Details

Kohima Station (Zubza) to Kohima City Center is final 15 km line.[5]

Route

Alignment revised to avoid populated areas.[5]

Current status

  • 2025 Jun: Expected completion is 2027–2028 due to the land acquisition disputes with local communities.[5]

Kohima-Imphal line

Details

Kohima-Imphal line, proposed ~220 km ₹ 25,000+ crore line will run through Patkai mointain ranage and require 50+ tunnels, route will be decided after FSL (Final Location Survey).[6]

Current status

  • July 2025: Proposed, but not yet surveyed, still in the pre-feasibility stage, hence likely to see progress only after 2030.[6]

Dimapur-Tizit line

Details

Dimapur-Tizit line, proposed, Rs4,274 ~257 km long line was approved in 2013, runs entirely within Nagaland along western border of Nagaland from Dimapur near southwest border of Nagaland till Tizit on northwest border of Nagaland near southeast-most Arunachal.[7]

Current status

  • May 2025: No further budget allocation has been made as of May 2025 official update and no completion deadline has been set because CCEA budget approval is awaited.[7]