Top Qs
Timeline
Chat
Perspective

Jammu–Baramulla line

Railway line in northern India From Wikipedia, the free encyclopedia

Jammu–Baramulla line
Remove ads

The Jammu–Baramulla line,[2] including the UdhampurSrinagarBaramula Rail Link (USBRL) subsection, is a 324 km long railway track between the cities of Jammu and Baramulla in Jammu and Kashmir India. It is fully operational as of June 7, 2025. Connecting the Kashmir Valley with the rest of India, this rail link has major geostrategic importance for the Indian armed forces. It has reduced the travel time between Jammu and Srinagar by 4 hours from 7 hours to 3 hours,[3] and it also connects the important religious pilgrimage sites of Mata Vaishno Devi Temple and Amarnath Temple.[4]

Quick Facts Jammu–Baramulla line Udhampur-Srinagar-Baramula Rail Link (USBRL), Overview ...

Completed in several phases, this link entails several engineering marvels including the Chenab Bridge - world's highest railway bridge, the Anji Khad Bridge - India's first cable-stayed railway bridge,[3] the Pir Panjal Railway Tunnel (Banihal railway tunnel) - India's longest railway tunnel as of 2025, [5] and the T33 tunnel, which, while short, is immensely challenging as it punches through the Main Boundary Thrust of the Himalayas.

Remove ads

History

Summarize
Perspective
Thumb
Jammu Tawi railway station.

In 1972, Prime Minister Indira Gandhi opened the newly laid railway line from Kathua to Jammu Tawi, and in 1983 she laid foundation stone for Jammu-Udhampur section of railway line. In 1994, while the Jammu-Udhampur line was still under-construction it's extension to Baramulla was announced by the Prime minister PV Narsimharao.

In 2005, Prime Minister Manmohan Singh inaugurates the operational Jammu-Udhampur railway line construction of which was delayed by 21 years,[6][7] He also inaugurated Anantnag-Mazhom section in 2008,[8][9] Mazhom/Pattan-Baramulla section in 2009,[10][11] Anantnag-Qazigund section in 2009,[12] Qazigund-Banihal section in 2013.

In January 2025, Jammu Railway Division was inaugurated by Prime Minister Narendra Modi as a newly created division carved out from the Firozpur Division, and the responsibility for the Jammu-Baramaulla line was transferred from Firozpur Division to Jammu Railway Division.[13]

Accidents

During the construction there were several fatal accidents, including death of Altaf Hussain, a Hindustan Construction Company (HCC) labour Altaf Hussain in June 2005 by a tunnel collapse in Tathyar, drowning of two girls in an excavated ditch on 16 May 2007, death of Nepali labour Tika Ram Balwari after being struck by a boulder in the Uri Varmul on 14 Feb 2008, the death of five occupants after a dump truck rolled into a deep gorge in Lower Juda More (near Kouri in Reasi district) on 18 Apr 2008,[14][15] and the death of two workers, Abdul Rahman (age 34) and Jumma Baksh (24) at Chenab River bridge on 27 Mar 2011 when the basket in which they were riding (attached to a crane) unhooked and fell over 100 metres.[16]

Remove ads

Features

Summarize
Perspective

The railway crosses over 750 bridges and pass through over 100 km (62 mi) of tunnels.[17]

Bridges

Thumb
Rail bridge in Banihal.

Main bridges are:[3][17]

  • Chenab Bridge:[3] 1,315-metre-long (4,314 ft) 11,215 m (6.969 mi) above the riverbed the arch bridge on the Chenab River is world's highest railway bridge as it is 35 metres (115 ft) higher than the top of the Eiffel Tower.[18] Design with similar structure to West Virginia's New River Gorge Bridge, the Chenab bridge construction used the weathering steel for an environmentally-friendly appearance and to also eliminate the need for painting.
  • Anji Khad Bridge: 657-metre-long (2,156 ft) bridge 186 m (610 ft) above the riverbed is India's first cable-stayed railway bridge.[3]

Tunnels

  • Pir Panjal Railway Tunnel (Banihal railway tunnel): 11.215-km (7-mile) long, 8.4 m wide and 7.39 m high tunnel is India longest rail tunnel in 2025, which also includes a 3 m-wide service road for maintenance and emergency use. Rail tunnel's average elevation of 1760 m is 440 m below the existing road tunnel.[5] The tunnel facilitates transportation during winter (when inclement weather closes the Srinagar-Jammu highway), and halves the distance between Quazigund and Banihal (35 km by road and 17.5 km by train).[19] The Banihal railway station is 1,702 m (5,584 ft) above mean sea level, and trains run from Banihal to Qazigund through the tunnel. The 5 km Banganga section was expected to be operational before the completion date of 2017–18 for the entire project.[20] Built with the New Austrian tunnelling method, and a number of challenges have been encountered while tunnelling through the geologically young, unstable Sivalik Hills, requiring drastic solutions with steel arches and several feet of shotcrete and lattice girder support.

Gradient

Although the rail line is being built through a mountainous region, a one-percent ruling gradient has been set to provide a safe, smooth, reliable journey. Bank engines will not be required, making the journey quicker and smoother. It will use 5 ft 6 in (1,676 mm) broad gauge continuous welded rail laid on concrete sleepers, with a minimum curve radius of 676 m. The maximum speed will be 100 kilometres per hour (62 mph).[18] Provision for future track doubling is made on major bridges.

Safety

There are Closed-circuit television cameras at major bridges, tunnels and stations, and all major bridges and tunnels are illuminated. Three-aspect colour-light signalling is installed on the route for safety, and GSM-R equipment will be installed in the future to improve its quality.

Maintenance

Maintenance workshop is at Badgam, north of Srinagar. It is owned-operated by Indian Railways's Jammu Railway Division of Northern zone.[3][21][22]

Remove ads

Construction

Summarize
Perspective

The total project cost in 2022 was INR28,000 crore (~US$3.5 billion).[23]

Challenges

Thumb
Training rounding a snow-laden curve in Qazigund.

The line was one of the most difficult rail project undertaken on the Indian subcontinent. The young Himalayas are geologically surprising and problematic.[18] The track's alignment presents one of the greatest railway engineering challenges ever faced; only Tibet's Qingzang Railway, completed in 2006 across permafrost and climbing to over 5,000 m (16,000 ft) above sea level, is comparable. Although the Indian temperatures are less severe, the region experiences harsh winters with heavy snowfall. In the Pir Panjal Range, most peaks exceed 15,000 ft (4,600 m) in height.

Construction entities

Thumb
Srinagar railway station with passenger train.

Indian Railways (IR) is overall responsible for the construction of 25-kilometre (16 mi) Udhampur-Katra section. IR's subsidiary Konkan Railway Corporation was responsible for the construction of 90-kilometre (56 mi) Katra-Laole section, arguably the line's most difficult portion, with over 92 percent tunnels or bridges—12 kilometres (7.5 mi) of bridges and 72 kilometres (45 mi) of tunnels. Ircon International, a public-sector company, was responsible for the construction of 175-kilometre (109 mi) Dharam-Qazigund-Baramulla section and Hindustan Construction Company built the 11,215 m (6.969 mi) Pir Panjal tunnel on this section at the cost of 900 crore.[24] Afcons Infrastructure Limited and South Korea's Ultra Engineering designed and built the Chenab Bridge for around ₹974 crore.[25] Gammon India and South Africa's Archirodon Construction built the Anji Khad Bridge for ₹745 crore.

Phases

The construction of railway line was divided into four phases:[18]

  • Phase-1, operational since 2005, 53 km long from Jammu to Udhampur, was built over 21 years.[6]
  • Phase-2, operational since 4 July 2014, 25 km from Udhampur to Katra,[26][27] includes 7 tunnels and 30 bridges.[28]
  • Phase-3, operational since 13 December 2024, 111 km from Katra to Banihal, has a total of 35 tunnels (includes 27 main and 8 escape tunnels),[3] 62 bridges and a number of tunnels totalling 10 km out of total 129 km route length was most difficult section of the overall project. It required 262 km of access roads connecting 147,000 people in 73 villages; 160 km, connecting 29 villages, is completed.[5]
  • Phase-4, operational since 26 June 2013, 135 km long section from Banihal to Baramulla runs across the Pir Panjal Range from Baramulla to Banihal.[29]
Remove ads

Route

Summarize
Perspective
More information Udhampur–Srinagar–Baramula Rail Link (USBRL) ...

This rail link makes several tourist and religious locations more easily accessible at faster travel speed and shorter travel time: Katra - the base town of the Vaishno Devi|Shri Mata Vaishno Devi shrine, Reasi, Pahalgam, Aharbal, Gulmarg, Verinag, Qazigund, Anantnag, and Mazhom near Pattan, Dal lake, Lolab Valley and Mughal Road.

Remove ads

Train services

Thumb
Banihal railway station.

Passenger services

Vande Bharat Express, air-conditioned, medium to long-distance train service operated by Indian Railways runs on this route.[3] The heated and air-conditioned coaches have wide windows, sliding doors, reclining seats, and a snow-cutting cattle guard is attached to the front of the train to clear snow from the tracks during winter. Due to the valley's cold climate, the 1,400-horsepower diesel engine has a heating system for quick, trouble-free starts. Coaches have a public-information system (display and announcements) and a pneumatic suspension for riding comfort. There is a compartment for the physically disabled, with wider doors.[30]

Freight service

Freight service (grain and petroleum products) run between the 10–12 daily passenger trains.

Remove ads

Future extension

See planned new rail lines in Jammu and Kashmir.

Alternate connectivity

Jammu-Baramulla line provides partial rail connectivity to Kargil and Leh, which have the following alternative existing and under-construction connectivity.

Present status

See also

References

Loading related searches...

Wikiwand - on

Seamless Wikipedia browsing. On steroids.

Remove ads