Railway line in Tokyo & Chiba prefectures, Japan From Wikipedia, the free encyclopedia
Remove ads
The Keisei Narita Airport Line (京成成田空港線, Keisei Narita Kūkō-sen) is a Japanese railway line connecting Keisei-Takasago Station and Narita Airport Terminal 1 Station. The entire route from Keisei Ueno Station, including the Keisei Main Line as far as Keisei-Takasago, is branded Narita Sky Access (成田スカイアクセス, Narita Sukai Akusesu).
The Keisei Electric Railway operates over the entire line, while other companies operate over certain sections of it, such as Hokuso Railway. The new line is used by Skyliner limited express services operating at up to 160 km/h (100 mph) using Keisei AE series EMUs.
Remove ads
Operations
Trains utilize the Keisei Electric Railway's Main Line between Keisei Ueno and Keisei-Takasago. Trains run at a maximum speed of 160 km/h (100 mph), thus completing the run from Nippori to Narita Airport Terminal 2·3 in a minimum of 36 minutes (15 minutes faster than the previous Skyliner route, which took 51 minutes). The reserved-seat Keisei Skyliner limited express fare for the route between Narita airport and either Nippori or Ueno stations is ¥2,580 and takes 36–41 minutes, while the Access Express commuter fast train costs ¥1,280 and takes 63–69 minutes.[1][2] Express trains also operate towards Haneda Airport from Narita Airport (in a long chain of through service via Keisei-Takasago, Aoto, Oshiage, Sengakuji/Shinagawa, and Keikyū-Kamata), connecting the two airports in 92–109 minutes for a fare of ¥1,850.
There are also plans to build a spur from the Toei Asakusa Line to Tōkyō Station, opening a (potentially) faster route to the airport via Keisei Oshiage Line.
Remove ads
Basic data
- Total length: 51.4 km (31.9 mi)
- Service operators and track owners:[* 1]
- Descriptions of the various categories are available at Rail transport in Japan.
Remove ads
Station list
Summarize
Perspective
Trains stop at stations marked "●" and pass those marked "|".[3] Some Skyliner trains stop at stations marked "▲".[4]
History

Service on this line commenced on July 17, 2010.[5] The line involved the refurbishment of 32.3 km (20.1 mi) of existing track on the Hokusō Line, as well as the construction of 19.1 km (11.9 mi) of new dual track to Narita Airport, partly using disused rights-of-way originally planned for the cancelled Narita Shinkansen project. The total cost, according to the Narita Rapid Rail Access website, was estimated to be ¥126 billion, or about US$1.3 billion.[6] From the timetable revision on February 26, 2022, Toei 5500 series trains began operating on the line on weekdays.[7]
In October 2022, Keisei announced that certain Skyliner trains would begin serving Shin-Kamagaya Station with the intent of improving access to Kashiwa and Matsudo in Chiba Prefecture.[8] The planned implementation took place on 26 November 2022.[9]