The Type 707 tankers are a series of replenishment oilers under construction for the German Navy to provide underway replenishment for its ships at sea. Procurement of two vessels was announced in July 2019, with delivery intended in 2025 to replace the Rhön-class tankers which are scheduled to be retired that same year.[2]

Quick facts Class overview, General characteristics ...
Remove ads

Project history

Summarize
Perspective

Background

The Rhön-class tankers required a replacement due to environmental concerns and their reliability decreasing due to the age of the fleet (in service since 1977).[6] The procurement project was decided in July 2019, with the intend back then to enter service in 2024.[7]

With this purchase, the German Navy will be equipped with 3 Berlin-class replenishment ships and 2 Type 707-class tankers.[7]

Tender

The tender process started in 2019. The German Navy provided their requirements for this class. The following table compares it to the Rhön-class tankers:[6]

Type 707 requirements[6]
Parameters Rhön-class tankers

(Type 704)

Planned Type 707
Requirements
Fuel capacity 11,500 t (25,400,000 lb) > 15,000 t (33,000,000 lb)
Containers 2 20
Speed 16 kn (30 km/h) 20 kn (37 km/h)
Complement 42
Dimensions
Displacement 20,000 t (44,000,000 lb) > 20,000 t (44,000,000 lb)
Length 130 m (426 ft 6 in) ~ 170 m (557 ft 9 in)
Beam 19 m (62 ft 4 in) ~ 24 m (78 ft 9 in)
Draft 8 m (26 ft 3 in) ~ 8 m (26 ft 3 in)
Other parameters
Hull type Double hull
Lifespan 2024 Beyond the 2050s

Selection

The competition saw five German shipyards competing for the contract, among which four shipyards are known:[8]

MV Werften and NVL Group were pre-selected as of April 2021, but the €550 million budget limit was not sufficient, and the bids of the two finalists were still €300 million above the target.[8]

The 23 June 2021, the budget committee approved the project for the Type 707 tanker, and the contract was later on signed with the NVL Group.[6] The budget is above €900 million for the two ships.[1]

Construction

Thumb
First MBV 707 - superstructure in transport from the Meyer Werft shipyard in Papenburg to the Neptun Werft shipyard in Warnemünde.
Thumb
Hull of the second ship afloat in the Kiel Canal
Thumb
Bow of the second ship made by Stahlbau Nord [de], in the Kiel Canal

The NVL Group is the general contractor of the project and it collaborates with the Meyer Neptun Group for the construction of the ships.[9] Two subsidiaries of the Meyer Neptun Group constructed the ships:[10][11]

Among the other main subcontractors are the Stahlbau Nord [de] shipyard in Bremerhaven which built some sections of the ships.[12][13]

First ship

The construction started the 29 June 2023 at the Meyer Werft shipyard in Papenburg with

the cutting of the first steel plate.[14] The keel was laid the 8 August 2023 at the Neptun Werft shipyard in Warnemünde.[15]

Second ship

The construction started the 29 February 2024 at the Meyer Werft shipyard in Papenburg with the cutting of the first steel plate.[10][16][17] The keel was laid the 25 April 2024 at the Neptun Werft shipyard in Warnemünde.[18]

The front part of the hull was transferred to the Meyer Werft shipyard in Papenburg in March 2025.[11]

Remove ads

List of ships

More information Name, No. ...
  Planned commissionning