Wardha–Nanded line

Railway line in Maharashtra, India From Wikipedia, the free encyclopedia

Remove ads

Wardha–Yavatmal–Nanded line, with 327 km long Wardha-Kalamb-Yavatmal-Digras-Pusad-Nanded alignment, is an under-construction railway line in Maharashtra state of India, which will connect Nagpur and other districts in Vidarbha with Nanded and other parts of Marathwada regions. It will reduce Wardha-Yavatmal psseger travel time from over 3 hours by road to approximately 1.5 hours by train. It will also provide evacuation of major produce of Vidharba, such as cotton, soybeans, and coal, to Marathwada.[1][2][3] It has been designated as the "special project" status by the Ministry of Railways, Government of India.[4][5]

Quick Facts Overview, Status ...
Remove ads

History

Revised total project cost of 284 km new line was INR3445.34 crores in 2025,[6][7] spanning across six tehsils and 90 villages in Wardha, Yavatmal, Washim, Hingoli and Nanded district of Maharashtra,[8] requiring acquisition of 722 hectares land.[9]

Route

Alignment

The final alignment of the Wardha-Kalamb-Yavatmal-Digres-Pusad-Nanded route has the following stations:[1][2][3]

  • Phase-I Wardha-Kalamb-Yavatmal
    • Phase-I.II Kalamb to Yavatmal, 40 km:
      • Wani Road (new)
      • Kelzar (new)
      • New Yavatmal (Yeotmal) (new terminal station is different from the existing Yavatmal junction city station.)
  • Phase-II Yavatmal-Digras-Pusad
Remove ads

Current status

  • Overall:
    • 2025 Jan: 47% physical work is complete with 85% of the total revised budget exhausted by 31 March 2025, likely to overshoot the budget.[6]
  • Phase-I Wardha-Kalamb-Yavatmal, completed and operational.[1][2][3]
    • Phase-I.I Wardha to Kalamb, completed and operational.[1][2][3]
    • Phase-I.II Kalamb to Yavatmal, completed and operational.[1][2][3]
  • Phase-II Yavatmal-Digras-Pusad, under-construction (2028 target):[1][2][3]
    • Phase-II.I Yavatmal-Digras, under-construction (2027 target): revised target as of June 2025.[1][2][3]
    • Phase-II.II Digras-Pusad, under-construction (2028 target): revised target as of June 2025 if land acquisition is resolved.[1][2][3]
  • Phase-III Pusad-Nanded, under-construction (2029 target): revised target as of June 2025 if protests and land issues are resolved.[1][2][3]

See also

References