Project 21180M is a series of icebreakers being built for the Russian Navy, developed by the Almaz Central Marine Design Bureau, intended as a cheaper alternative to the larger and more expensive Project 21180.[1][7]

Quick Facts Class overview, General characteristics ...
Remove ads

Development and construction

Summarize
Perspective

In the mid-2010s, the Ministry of Defence of the Russian Federation announced that a fleet of new auxiliary icebreakers would be built for the Russian Navy as part of the ongoing fleet renewal program to replace Soviet-era vessels.[8] However, the initial plans for the construction of four 6,000-tonne (5,900-long-ton) Project 21180 icebreakers was revised after the lead ship, Ilya Muromets, turned out to be too expensive. Consequently, Vympel Design Bureau developed a revised design, Project 21180M, with about two thirds of the displacement and more limited functionality compared to the bigger vessel.[9][10]

The construction of the first Project 21180M icebreaker was awarded to Almaz Shipbuilding Company in 2017.[9] The vessel was laid down on 12 December 2018,[11] launched on 24 November 2020,[12] and delivered to Russian Navy on 1 July 2024 after having been towed from Saint Petersburg to Petropavlovsk-Kamchatsky in the previous year.[13][14] Evpatiy Kolovrat, named after the 13th century bogatyr described in The Tale of the Destruction of Ryazan, entered service with the Pacific Fleet on 26 July 2024.[15]

The keel of the second vessel was laid down on 1 September 2023.[16] The vessel will be named Svyatogor after the mythical bogatyr and its delivery to the Northern Fleet is envisaged for 2027.[17]