Rail line in Songjiang District, Shanghai From Wikipedia, the free encyclopedia
Remove ads
Songjiang Tram (also Songjiang Tramway) is a light rail tramway in Shanghai, China. The system consists of two lines (T1 and T2) totaling 31 km (19 mi) with 42 stations.[2] Unlike the Zhangjiang Tram, Songjiang trams use centenary power supply and steel-wheeled rail systems. Most of the route follows independent rights of way. Intersections with other road users give priority to trams allowing for running speeds of 25-30km/h. Trains run from 6:00 till 22:00. With further extension of the network public transport modal split in Songjiang is expected to increase from the current 23% to 40%.[3]
The tram system is operated by 30 light rail vehicles (LRVs),[4] while other 4 lines in development of line directions. Estimated ridership for the line is 170,000 passengers per day.[2][5]
A joint venture between Shanghai Shentong Metro Group and Keolis’ Chinese joint venture, Shanghai Keolis, with Shanghai Shentong Metro Group holding 51%, has been awarded a five-year contract to operate and maintain the line.[2]
Remove ads
Pricing schedule
The fee is 2 yuan within 10 kilometers (inclusive) with an extra 1 yuan charge for each additional 10 kilometers. Children under 1.3m in height travel for free (accompanied by an adult).
Each station of Songjiang Tram is equipped with an automatic ticket vending machine. Shanghai Public Transport Card (physical card and mobile phone transportation card) can enjoy preferential transfers. The transfer discount policy for Shanghai public transport service is applicable, where when transferring to bus, subways or trams within 2 hours, the price is reduced by 1 yuan.
Since June 30, 2023, beside Shanghai Public Transportation Card, QR codes (WeChat, Alipay, etc.) and Transportation Union Cards from other regions are also supported in Songjiang Tram.[6]
Remove ads
History
Summarize
Perspective
Opening timeline
Note: The first phase of Songjiang Tram T2 Line includes Songjiang Tram T5 Line Thames Town West Station-North Sanxin Road Station. After the completion of Songjiang Tram T5 Line, this section will be operated by Songjiang Tram T5 Line.
The first 13.9 km (8.6 mi) section of the system, with 20 stations, opened on 26 December 2018.[8]
A 12.864 km (8.0 mi) section (including the remaining section of T2, and part of T1) opened on 10 August 2019.[9]
The remaining section of T1 (from Xinqiao Railway Station to Xinmiaosan Road) opened on 30 December 2019.[10] The section is 3.881 km (2.4 mi) in length.[10]
In 2020, the Songjiang tram T2 line construction project won the 2018-2019 Shanghai Municipal Engineering Gold Award.[11]
The opening time of Chenta Road station on T1 is still unknown.
Passenger flow
- From December 26, 2018 to February 9, 2019, the total passenger flow of Songjiang tram T2 line reached 478,334, and the average daily passenger flow was 10,398.[12]
- From December 26, 2018 to April 4, 2019, Songjiang tram T2 line transported a total of 1.084 million passengers, with an average daily passenger flow of 10,845, of which a single-day passenger flow reached 20,314 on December 31, 2018.[13]
- From the opening of trial operation on December 26, 2018 to June 25, 2019 the total number of passengers carried was 2,108,687, the average daily passenger flow was 11,586, and the maximum passenger flow in a single day was 20,478.[14]
- In 2021 the total passenger flow of the two lines is 9.1778 million; the average daily passenger flow of the two lines 25,100 passengers, and the highest passenger flow in a single day occurred on December 31, 2021, with 38,000 passengers.[15]
Remove ads
Stations
Summarize
Perspective
Songjiang Tram T1
All stations are in Songjiang.
Songjiang Tram T2
The current operating mileage is about 14.0 kilometers with 20 stations (excluding the common line section).
All stations are in Songjiang
Remove ads
Future expansion
Summarize
Perspective
Under construction
The west extension of the T2 line started construction on 19 February 2021.[16] It runs from Sanxin North Road to Xiangkun Road, with a total of 9 stations, with a total length of about 7.4 kilometers. The line runs along Xinsongjiang Road, Wensong Road, Dingsheng Road, and Wenxiang Road from east to west, with a total of Sanxin North Road Station, Chenta Road Station, Dingyuan Road Station, Dingsong Road Station, Dingwen Road Station, and Dingsheng Road. 9 stations including Lu Station, Hexi Street Station, Kunde Road Station and Xiangkun Road Station.
In order to meet the needs of line parking and operation management, it is proposed to set up a Xiaokunshan parking lot, located at the starting point of the western section of the second phase of the project, at the northwest corner of the Xiangkun intersection of Wenxiang Road, with a total land area of approximately 0.97 hectares. At the same time, in order to ensure the operation needs of the west extension of the T2 line, a total of 5 substations have been set up across the line, of which one civil substation is combined with a parking lot, and the other 4 are box-type substations.
Future plans
Eventually the plans call for 7 tram lines with a total length of about 150km.
- The long-term planning line announced in September 2013, the line planning is already old
- Songjiang tram future plans in 2018
- Songjiang tram under construction
Remove ads
Technology
Depots and yards
- Chenta Road Depot is a depot for Line T1. It has inspection lines and temporary repair lines, and can also carry out work such as overhauls. Up to 77 trains can be stored.
- Xinqiao Yard is a stabling yard of Line T1, which can store 8 trains.
- Songjiang University Town Yard is a stabling yard of Line T2. It has inspection lines and temporary repair lines. It can also receive new cars, repaired cars, and complete overhauls. Up to 33 trains can be stored.
Rolling stock

A joint venture of Alstom and Shanghai Rail Traffic Equipment Development Company was awarded a €72 million contract in April 2015 to supply 30 Alstom Citadis 302 trams. The first Silkworm low-floor LRV was delivered on 21 November 2016.[17] The trams can carry 300 passengers.