Haibang Station (Chinese: 海傍站; Cantonese Yale: Hóibohng Jaahm) is an interchange station between Line 3 and Line 4 of the Guangzhou Metro.[1] The Line 4 station started operations on 30 December 2006 and is located at the junction of Changnan Road.[2] and the Jingzhu Expressway in Shiqi Town (石碁镇), Panyu District.[3] The Line 3 station started operations on 1 November 2024.[4]
Remove ads
Station theme
It is the theme station of the east extension of Line 3, with the design theme of "Chasing the Water Facing the Sea". The ceiling of the station adopts a gradient color wave shape, and the wall is decorated with watercolor wave patterns to show the local characteristics of the Shatian Water Town style.[5]
Station layout
F2 Platforms |
Side platform, doors will open on the right | |
Platform 4 | ![]() | |
Platform 3 | 4 towards Huangcun (Shiqi) ![]() | |
Side platform, doors will open on the right | ||
G Concourse |
Line 4 Lobby | Customer Service, Shops, Vending machines, ATMs, Exits, Toilet |
B1 Concourse |
Line 3 Lobby | Ticket Machines, Customer Service, Shops, Safety Facilities, Transfer passageways between Lobbies |
B2 Platforms |
Platform 1 | ![]() |
Island platform, doors will open on the left | ||
Platform 2 | 3 towards Tianhe Coach Terminal or Airport North (Terminal 2) (Haichong Lu) ![]() |
Remove ads
Exits
Gallery
- Line 3 concourse
- Line 4 concourse
- Transfer level between the two lines
- Line 3 alighting platform
- Line 4 platform (towards Nansha Passenger Port)
History
Summarize
Perspective
The project of the eastern extension of Line 3 was approved by the National Development and Reform Commission in late March 2017, and the construction report was approved in early January 2018,[6] followed by the construction of the station part of Line 3 in mid-2019.[7] On 1 July 2023, the tunnel boring machine broke through, and on October 27, the main structure was topped out.[8] The "three powers" transfer was completed on 31 May 2024.[9] On 1 November 2024, the eastern extension of Line 3 was put into operation, along with the station.[10]
Line 3 opening complications
The natural gas pipelines that affected the opening of Qingsheng Station and Guangzhou Metro Line 22 earlier once brought uncertainty to the partial opening of Line 3 of this station.[11] In 2022, the authorities issued a notice stating that the expansion of Haibang station would have affected the operation of the existing three pipelines, namely Guangzhou Gas, Dapeng Gas and Sinopec Pipeline, and they would need to be relocated.[12][13] The Dapeng Gas Pipeline and Sinopec Oil Pipeline started construction and relocation in December 2023 and March 2024, respectively, and are scheduled to be completed in March 2025.[14] The Guangzhou Gas Pipeline will be relocated and renovated by the Guangzhou Metro Group itself, and the relocation began as of October 2024.[15]
Although the station had already been handed over to the subway operation department for commissioning, the latter was even ready to open the station at the end of September 2024, but this did not happen.[16] The authorities have responded that the station of Line 3 can only be opened after the construction of the pipeline is completed and the pipeline is accepted.[17] However, it was not until October 30 that the Guangzhou Metro Group announced that the eastern extension of Line 3, including this station, would open on November 1 of the same year.[4]